Bioethanol Plant

Location
Saltend, Hull

Engineers
Aker Solutions / Peers

Value
£9,000,000

The project included 3500 tonnes of primary steelwork and 500 tonnes of secondary steel, flooring, handrailing and ladders. The scope of work comprised the design and build of Modular Piperacks consisting of 22 No PARs and support towers which were delivered in units complete with M & E installed. Peers carried out the detailed engineering, fabrication and erection of the Main Process Structures loading the key items of plant during the build.

Previous ImageNext Image

Covid-19 Risk Assessment Update

Peers have recently carried out several Risk Assessments to ensure the health and safety of its employees and visitors during this global Pandemic. We will continue to monitor the news and guidance around the Pandemic and update accordingly.

COVID 19 Factory Control Measures all business unit summary COVID 19 Office Control Measures all business unit summary COVID 19 Construction Control Measures all business unit summary

Contact Information

  • Harry Peers Steelwork Limited
  • Elton Street
  • Mill Hill
  • Bolton
  • Lancashire
  • BL2 2BS (For SatNav use BL2 2BU)
  • For directions see our Contact Page
  •  
  • Tel: 01204 558500
  • email post@peers.co.uk

Please send all correspondence to Head Office at Elton Street,Bolton,BL2 2BS.
We cannot be held accountable for correspondence sent to any other address.